Ring the bell for success…..
CELEBRATING GREAT WORK, BY GREAT PEOPLE IS A PART OF THE GILL’S ORGANIZATION. WHEN ONE OF OUR TEAMMATES COMPLETES A PROJECT IT IS THEIR OPPORTUNITY TO CELEBRATE AND RING THE BELL.
Congratulations to Tamaya and the team on completing the R2 Utilities Modifications project. Even though the project was straightforward, some indecisiveness regarding the SOPs resulted in a lot of back and forth and cost us a lot of time. But Tamaya and the team persevered and successfully completed the project. Thank you all for your hard work!
Congrats to the Three Amigos pictured above! The former Client Computer QA Director had required that an ERES assessment be performed on the legacy Metasys program. This requirement was ignored for years, until a CAPA drove its completion. That's when Gill's was given a PO to "make this go away". First, Maury generated and executed a supplemental OQ protocol to provide objective evidence of data integrity compliance. Then, Venu generated a Metasys Alarm Assessment that was needed. And finally, Mahesh generated the required ERES assessment and expedited its approval to meet the CAPA deadline!
Thanks guys, for your diligence in putting this to bed!
Great job Prudvi for completing the Decommissioning of the two QCC Agilent HPLC 1100 with the Change Record approved on 11/19 for implementation. We appreciate all of your hard work and dedication to serve the client!
Congrats to this Dynamic Duo! Krystal and Mahesh implemented a change to configure new Metasys equipment controllers to the existing Munters Dehumidifiers that pretreat the ambient air for an entire facility. Before these controllers were installed, the HVAC crew had to trek up to the local dehumidifier HMIs in the building mezzanine to make any adjustments. Now, the HVAC techs can monitor/control the airflow from the comfort of their office.
Venkat completed the protocols that disconnected Still 5 and 8 from the ambient WFI header, removed the old Line WFI POU and the facility qualification protocol in an Aseptic Pack off.
Congrats to Gene for completing the Utility Qualification on a modification to the High Quality Steam in a client business unit. This would have been completed last year, except a previous contractor installed a cap of the wrong material!
Thanks, Gene for putting this headache to bed.
Elijah successfully completed the commissioning of the warehouse backup generator. The project was to coordinate the movement, placement, and the start-up test to put back the generator after the Hi-Rise demolition. Elijah worked with several vendors that were used on the project at the client site to compete the commissioning.
Also, a special thanks to Matt and documentation team for getting this completed.
Big thanks to Prudvi for supporting his fellow teammates on the QCC implementation of the Perkin Elmer PinAAcle 900T with the change record approved on 11/4. Great work getting the job done! Thanks for all you do in representing Gill’s in excellent work.
Congrats to the Lone Ranger again! Mahesh managed and executed a Change Control to decommission a legacy version of the AMPS software and server used in Central Drug Weigh and Dispense when the site upgraded to the latest version. The project was delayed numerous times due to corporate SME staff turnovers, but Mahesh persevered.
Goutham was able to complete a supplemental protocol when a Data integrity issue was identified with a Bag Sealer. kudos for working fast and efficiently to get the job done!
Congratulations to Dheeraj and Vyvika on closing the binder for 'Modifications to the Metasys system due to the areas declassified in Flex and VisIV'. They inherited this project with very limited hours and worked efficiently with another contractor on completing the project successfully.
Great job guys!